Remote configuration of safety devices enables better monitoring and faster response to system changes. Installation of telemechanics switchgear and safety device concentrators ensures effective supervision of electrical equipment.
Modernization of 15 kV distribution fields resulted in reduced system failure rates, replacement of transformers and switchgear contributed to improved station operation stability and also met requirements for extending critical infrastructure power supply maintenance time.
Effective response to potential failures thanks to remote configuration of safety device parameters enables faster identification and elimination of faults.
The modernization project of four RSM 15kV stations provided a response to the needs of increased efficiency, safety and reliability of emergency response in the power supply system. Project implementation, despite challenges related to costs and work organization, brought significant benefits in the form of remote supervision and control over equipment, failure reduction and improved incident response. Thanks to cooperation with the investor and engagement of all parties, the project ended successfully, introducing significant improvements in electrical infrastructure.