CLIENT
PGE Dystrybucja S.A.
LOCATION
Pabianice, Sieradz, Sulejów, Radomsko, Łódź, Roszkowa Wola, Żyrardów, Brzeziny
YEAR
2024 - 2025
+9
new rectifiers
+1166
battery cells replaced
Challenge
The service life of many substation batteries was ending: capacity had become too low, rectifiers were damaged, DC wiring was obsolete and telecontrol links were absent. EU Regulation NC ER on system restoration also imposed new requirements. Most substations still had only a single battery section, so temporary batteries had to be installed during replacement. This involved additional risk because each station needs continuous DC supply to remain online for dispatch. The works had to be performed on substations in Retkinia, Janów, Sulejów, Lodowa, Pabianice, Roszkowa Wola, Komuna Paryska, Sieradz, Jawor, Żyrardów and Brzeziny.
Solution
At every listed site we replaced the battery sets with new, higher-capacity units, supplied matching racks and new cabling, and installed enlarged DC protection boards that allow a portable battery with rectifier to be plugged in. Missing LEM measurement transducers were added, defective rectifiers were replaced (or additional primary rectifiers installed) and a telecontrol link was configured so dispatchers have remote visibility of signals and measurements.